Agriculture TrendsAgriculture Trends
  • Home
  • News
  • Business
  • Insights
  • Crops
  • Livestock
  • Machinery
  • Technology
  • Farm Management
  • Weather
  • More
    • Web Stories
    • Press Release
    • Trending

Subscribe to Updates

Get the latest agriculture news and updates directly to your inbox.

What's On
AFBF: Cash rents up 3.2% as commodity prices slide

AFBF: Cash rents up 3.2% as commodity prices slide

August 8, 2024
How farms have fared as Debby delivers hard blow to Southeast U.S.

How farms have fared as Debby delivers hard blow to Southeast U.S.

August 8, 2024
New USDA rules aim to strengthen farm financial stability

New USDA rules aim to strengthen farm financial stability

August 8, 2024
Facebook X (Twitter) Instagram
Agriculture TrendsAgriculture Trends
  • Privacy Policy
  • Terms of use
  • Advertise
  • Contact Us
Facebook X (Twitter) Instagram
SUBSCRIBE
  • Home
  • News
  • Business
  • Insights
  • Crops
  • Livestock
  • Machinery
  • Technology
  • Farm Management
  • Weather
  • More
    • Web Stories
    • Press Release
    • Trending
Agriculture TrendsAgriculture Trends
Home » New scorecard rates nation’s grid managers on connecting renewables

New scorecard rates nation’s grid managers on connecting renewables

March 18, 20246 Mins Read Business
New scorecard rates nation’s grid managers on connecting renewables
Share
Facebook Twitter LinkedIn Pinterest WhatsApp Email
New scorecard rates nation’s grid managers on connecting renewables

by Robert Zullio

Across the country, electric demand is growing and could explode if green goals like electrifying home heating, industry, and transportation come to fruition. At the same time, many states, utilities, and businesses have pledged to decarbonize, helping push older coal and gas power plants that have struggled to stay economically competitive into retirement.

Yet in the queues run by the organizations that manage the electric grid in much of the nation, more than two million megawatts of potential new power sources, chiefly solar, wind and batteries, are languishing awaiting interconnection studies.

That dynamic prompted Advanced Energy United, a trade group representing clean energy businesses, to publish a first-of-its-kind scorecard grading how well the seven regional transmission organizations, which coordinate the flow of electricity for roughly two thirds of American electric customers, are doing at getting new projects approved to connect to their grids.

The short answer? Not so great. But some regions have been better than others, according to Caitlin Marquis, managing director at AEU. Both the Electric Reliability Council of Texas and the California Independent System Operator, organizations that manage the grid in most of their respective states, got Bs. The other five organizations got grades of C-  or lower.

“Grid managers have moved too slowly to adapt to changing market conditions, allowing the process of connecting new electricity to the transmission grid to become dysfunctional,” she said in a statement. “Without urgent improvement, the U.S. grid may struggle to keep up with growing energy demands, threatening our ability to keep the lights on and reach our climate goals.”

Grid operators push back on ratings

In many regions, interconnection – the usually multi-year process to connect new power generators to the transmission system, including studies of any upgrades needed to ensure reliability – has been a well-known problem for years.

Last summer, the Federal Energy Regulatory Commission issued new rules intended to help clear the backlogs. And indeed, some grid operators questioned the point of the scorecard, which uses data that in some cases is several years old. They said the problems have long been acknowledged and that they’ve been working to overhaul their interconnection processes.

“The report is an assessment of conditions and practices that no longer exist,” said Jeff Shields, a spokesperson for PJM, the nation’s largest grid operator with a service area that includes 65 million people. “PJM and its stakeholders acknowledged those issues over three years ago and reformed our interconnection process.” PJM got a D- on the scorecard.

Mary Cate Colapietro, a spokesperson for ISO New England, which got a D+ from AEU, also questioned the merits of the exercise.

“It is not clear what the value of such a report is given that ISO New England and other regional system operators are in the process of developing significant changes to the interconnection process,” she said.

Both PJM and MISO, the grid operator for a large swathe of the central U.S., pointed out in their responses that thousands of megawatts’ worth of new energy projects have made it through their queues but haven’t been built because of financing, siting and supply chain problems.

“This is the challenge we need to confront as an industry rather than looking back on problems that have been largely addressed,” Shields said.

Brandon Morris, a MISO spokesperson, said more than 50 GW of new generation facilities have  been approved by MISO, “but many are not going into service on schedule due to supply chain issues and permitting delays that are beyond MISO’s control.”

Nonetheless, AEU says the report is an important baseline that will help gauge how well the grid operators implement the fixes federal regulators have mandated.

“This report reflects the challenges that project developers and engineers are dealing with not just a few years ago, but right now,” Marquis told States Newsroom. “While reforms are being planned, and in some cases implemented, they don’t address all the concerns outlined in the report, and they aren’t yet fully in effect. One thing the report demonstrates is that even when procedures work on paper, they don’t always work so well in practice.”

Rob Gramlich, an electric grid expert and president of Grid Strategies, a consulting firm that helped prepare the scorecard, pointed out that the 12 interviews conducted with generation developers and engineering firms are all people who are going through the interconnection process now. The grades were determined by considering six factors, two of which were customer perspectives on timeline and costs. The others are speed and certainty, number of interconnection agreements signed, average costs and cost certainty.

“We would expect all of them to improve somewhat if we did it in a year or two,” Gramlich said. “We were just looking at a snapshot today.”

MISO

The Midcontinent Independent System Operator manages a portion of the North American electric grid stretching from Manitoba, Canada, to the Gulf of Mexico. In that territory are all or parts of 15 states, including Iowa, and 45 million people.

MISO’s interconnection study process is “unreliable and slow,” the report says.

“MISO’s timeliness challenges have become particularly evident recently, as queue sizes have increased,” the scorecard says. “While MISO used to share details with interconnection customers on the reasons for delays, over the past two years these updates have become less dependable.”

Brandon Morris, a spokesperson for MISO, said the organization’s approach to bringing new power resources into the system “continues to be one of the most efficient in the electric industry” and that its process was highlighted by FERC as a “positive example” for other organizations.

“We have implemented reforms over the past few years to ensure our interconnection process is not an impediment to having the necessary generator resources available when needed,” Morris said.

However, developers working with MISO aren’t so sure things will get much better, the scorecard says.

“Although MISO’s recent study enhancements to limit system impact study duration are intended to reduce queue processing to 373 days, interconnection customers still anticipate that most projects will take three or more years to complete, especially in MISO-West,” according to the report.

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

Related Posts

Chasing 8 Stunning Waterfalls In Munnar

Chasing 8 Stunning Waterfalls In Munnar

August 7, 2024 Business
Chasing 8 Stunning Waterfalls In Munnar

Mentawais For Longboarders And Beginner To Intermediate Surfers

August 6, 2024 Business
Some hard life lessons are learned in the 4-H show ring

Some hard life lessons are learned in the 4-H show ring

August 6, 2024 Business
Chasing 8 Stunning Waterfalls In Munnar

5 Mesmerizing National Parks In Himachal Pradesh

August 5, 2024 Business

Brody Malone’s rodeo roots helped fuel Olympic success

August 2, 2024 Business

Iowa State Fair gives a sneak peak of the 2024 butter cow

August 1, 2024 Business

Leave A Reply Cancel Reply

Don't Miss
How farms have fared as Debby delivers hard blow to Southeast U.S. News

How farms have fared as Debby delivers hard blow to Southeast U.S.

By staffAugust 8, 20240

Some farms are under water and the U.S. Department of Agriculture has pledged resources to…

New USDA rules aim to strengthen farm financial stability

New USDA rules aim to strengthen farm financial stability

August 8, 2024
Viewpoint: The uglier side of solar farming is impacting agriculture

Viewpoint: The uglier side of solar farming is impacting agriculture

August 8, 2024

2024 election heats up over Harris’ red meat statements

August 7, 2024

Subscribe to Updates

Get the latest agriculture news and updates directly to your inbox.

Our Picks

College Aggies Online announces mentor and rancher Natalie Kovarik

August 7, 2024

N.C. man pleads guilty in $1 million livestock theft scheme

August 7, 2024
Chasing 8 Stunning Waterfalls In Munnar

Chasing 8 Stunning Waterfalls In Munnar

August 7, 2024
EPA takes historic action to halt specialty-crop herbicide

EPA takes historic action to halt specialty-crop herbicide

August 7, 2024
Agriculture Trends
Facebook X (Twitter) Instagram Pinterest
  • Privacy Policy
  • Terms of use
  • Advertise
  • Contact Us
© 2026 All rights reserved. Agriculture Trends.

Type above and press Enter to search. Press Esc to cancel.